4.0 It is clear from Central Government guidance that a key feature of Area Action Plans should be their focus upon implementation. As well as identifying the distribution of land uses, site-specific development proposals, associated infrastructure and other improvements (as set out in Part C of this plan) an AAP should also set a broad timetable for their delivery and implementation.
4.1 Accordingly, it is important that the proposals within the Longbridge AAP are both deliverable and viable within the timeframe of the plan. In addition, it is believed that the Longbridge AAP should also act as a wider ‘catalyst for change’ and have a strong role to play in stimulating regeneration in its widest sense including focusing the delivery of local area-based regeneration initiatives and socioeconomic programmes.
4.2 The implementation of the Longbridge AAP over the life of the plan will be very dependant upon: Commercial interest in the types and mix of land uses proposed. The levels of on site constraints and development costs. Financial returns on remediated land and packaged sites. The viability of schemes at the time planning applications are submitted. Implementation of public sector initiatives and availability of public sector and other stakeholder funding, including co-funding or gap funding, as necessary.
4.3 A detailed viability model has been established for the Longbridge AAP, which underpins and supports the proposals established in this document. An ‘open book’ approach has been taken with the main developer to broadly agree the variables within the model. The model has enabled the local authorities to:
4.4 Details of the viability model are provided in the technical baseline report on viability and deliverability, which supports this document.
4.5 The development will require an element of public funding and further information on this is set out in table 5 and in Appendix 5.
In addition, the previously developed nature of the site, which requires substantial remediation and other abnormal costs, means that viability is likely to be an issue in times of difficult market conditions. In such circumstances a flexible approach to any negotiations at planning application stage will be required to ensure viability and that the delivery of an acceptable scheme on the ground is not constrained or delayed. The approach to such negotiations is set out in paragraph 4.25 below.
4.6 The redevelopment of Longbridge will result in 10,000 jobs, a minimum of 1,450 new dwellings and approximately 3,500 new residents. This creates a need for a range of physical and community infrastructure and other measures, without which:
4.7 In terms of planning obligations, these may require the developer to carry out certain prescribed works to provide the appropriate infrastructure and measures (e.g. requiring that a certain proportion of housing is affordable); and/or mitigate the negative impacts of a development and to ensure that it makes a positive contribution to the communities within which it is situated (e.g. through environmental mitigation measures and increased public transport provision). These types of obligations, which are in line with Planning Obligations Circular 05/05 are identified in the site-specific proposals in Section C of the Plan and Tables 1 and 2 below.
Where appropriate, planning conditions will also be used to secure infrastructure and other measures.
4.8 The local authorities involved in producing the Longbridge AAP have agreed a planning contributions model, which consists of both traditionally negotiated S106 elements, such as affordable housing, and a simple Longbridge Infrastructure Tariff (LIT), to support the development of the area. This approach could have several advantages including:
4.9 The planning contributions model also sits alongside a package of S278 and S38 agreements for the private sector and other stakeholder funding of works on local and strategic roads as required by proposals in the Movement Strategy. The S278 agreements provide a well tested financial mechanism for ensuring delivery of mitigation works identified and determined as necessary for planning permission to be granted. Table 1 provides information on the key anticipated S278 requirements as part of the Longbridge AAP.
4.10 Agreements will also be required under Section 38 of the Highways Act 1980 for roads to be adopted within the development sites. There will be further standard agreements for the adoption of sewers, footways and other structures.
Table 1: Anticipated S278 Scheme Requirements
ITEM |
RATIONALE |
PHASING |
A38 Road Improvements |
Requirement has emerged from the traffic modelling work and is detailed in the AAP Movement Strategy (T8). Includes A38 improvement, junction works, street trees and sound attenuation measures. |
Links with River Rea Re-profiling |
Longbridge Lane |
Requirement has emerged from the traffic modelling work and is detailed in the AAP Movement Strategy (T8). Includes on and off site improvements to Longbridge Lane (including junction improvements, modest widening and improvements to A441 roundabout) and any appropriate traffic management measures on adjacent roads. Also includes environmental enhancements at the Sunbury Road centre and street trees. |
Links to development of North and West Works |
Groveley Lane |
Requirement has emerged from the traffic modelling work and is detailed in the AAP Movement Strategy (T8). Includes bridge works, junction improvements, street trees, crossings and lighting. Also includes environmental enhancements in centre at Groveley Lane / Parsonage Drive. |
Links to early phase of East Works redevelopment |
Tessall Lane |
Requirement has emerged from the traffic modelling work and is detailed in the AAP Movement Strategy (T8), Includes junction improvements at A38. |
Links in with A38 |
Lickey Road and Lowhill Lane |
Requirement has emerged from the traffic modelling work and is detailed in the AAP Movement Strategy (T8). Includes realignment of Lickey Road at A38 junction, junction improvements at Lickey Road / Lowhill Lane and environmental works on Lowhill Lane including street trees. |
Links to completion of East Works 1st phase |
Parsonage Drive Area |
Improvements identified by local residents and outlined under AAP Movement Strategy (T15). Traffic calming and access improvements. |
Links to completion of East Works 1st phase |
M5 Junction 4 and M42 Junctions 1 & 2 |
Requirements have emerged from the traffic modelling work and are outlined in the AAP Movement Strategy (T14), to include junction work and improvements to approach roads. |
Links to completion of local centre |
A441 Hopwood |
Improvements identified through traffic modelling and outlined in the AAP Movement Strategy (T13), to include traffic management measures, crossings and other works between the M42 and Longbridge Lane. |
Links to completion of East Works 1st phase |
Public Transport Interchange/Longbridge Lane |
Supported in bus strategy and outlined in the AAP Movement Strategy (T5), to include new high quality passenger waiting facilities, real time information points, taxi waiting areas, bus turning facilities and strong physical connections to Longbridge Railway Station. |
Links in with other Longbridge Lane improvements |
4.11 The planning contributions associated with the Longbridge AAP are split into traditionally negotiated agreements under Section 106, and a supporting Longbridge Infrastructure Tariff (LIT), which covers both residential and non-residential elements of the development. If the scheme is not viable at the time of submitting planning applications there will be a need for negotiations on the application, including the S106 and LIT elements, and taking account of the availability of public sector and other stakeholder funding. The approach to this is set out in para 4.25 below.
4.12 Section 106 Agreements The elements of the scheme for negotiations include: A target of 35% affordable housing across the site. Securing the provision of community, library, health, recreational and cultural facilities within the overall development and the provision of ‘The Austin’ building within the local centre and space within it for a variety of users as well as the provision of new library/community centre as part of the redevelopment on the former East Works site. Securing an appropriate level of affordable business space. Establishing requirements for site specification and phasing of river infrastructure (River Rea and River Arrow). Establishing requirements and specification for the urban park and local neighbourhood parks, walkways and cycle-ways.
Agreements covering design and construction standards for residential and non-residential buildings. Ensuring that carbon emissions from development are minimised in line with the area-wide sustainability strategy. Agreements on overall site phasing, upfront infrastructure and the timing of reserved planning application matters. Securing 15 year open space and local centre/town centre management agreements. Triggers for payment of LIT contributions, longstop dates when outstanding payments are due, as well as the indexation of levy contributions.
4.13 Longbridge Community Infrastructure Improvements With regard to the LIT, infrastructure has been defined by the joint charging authorities (Bromsgrove District Council and Birmingham City Council) as ‘infrastructure of local and strategic importance to the delivery of sustainable developments’. Table 2 summarises a broad schedule of anticipated community infrastructure improvements to support the Longbridge AAP. Further information on the community infrastructure requirements including outline costs, information sources and methods of calculation are included in the Longbridge Viability and Deliverability Technical Baseline report.
Table 2: Anticipated Community Infrastructure Improvements
THEMES AND COMPONENTS |
RATIONALE |
PHASING |
Longbridge Railway Station |
Identified in the Rail Strategy and supported in AAP Movement Strategy (T6) to include re-fit and upgrading of existing station and the accommodation of additional services. |
Link to Longbridge Lane improvements |
Rail service and infrastructure improvements – Longbridge/ Bromsgrove and Redditch |
Identified in the Rail Strategy and supported in AAP Movement Strategy (T12). Key focus on enhanced track capability to allow more stopping services at Longbridge Station and beyond. Also includes enhanced stations and services. |
Links with completion of local centre and early phases of RIS |
Bus Service Improvements |
Supported in the Bus Strategy and AAP Movement Strategy (T4) to include an extensive network of quality local bus services within the site, the redirection of existing services and improved longer distance services. Bus service improvements also include dedicated infrastructure within the development to serve Frankley. |
Links with commencement of local centre and early phases of RIS. Timetable to include early trial of Buzz Bus network |
Physical, Social, Recreational and Ecological Infrastructure
THEMES AND COMPONENTS |
RATIONALE |
PHASING |
Education and childcare – Nursery, Creche, Primary and Secondary Schools |
Priorities identified in the Community Infrastructure Baseline and AAP Sustainability Strategy (S2) to meet the needs arising from the provision of new dwellings to include investment in existing school facilities in both local authority areas and new pre-school services. |
Links to delivery of housing. New facilities to be available on completion of first phases of new housing |
Public Art |
Identified in the Cultural Baseline and AAP Design Strategy (DS1), on and off-site public art infrastructure (including arts development resources) with maintenance support for physical structures. |
Phased throughout development of highway works |
Cofton Park- open space, recreational, community and visitor facilities |
Various baseline support improvements also detailed in the AAP Environment, Open Space and Landscape Strategy (Proposal OS1). To include enhanced play pitches, multi-use games area, landscape improvements, site drainage, and ecological measures. Other priorities include the re-use of Lowhill Farm for community use with changing facilities and toilets; enhancement of Cofton Green Waste Recycling Centre and Cofton Horticultural Centre with improved customer facilities and greenhouses. Bus service improvements also include dedicated infrastructure within the development to serve Frankley. |
Links to delivery of housing. Works to coincide with completion of early phases of H1 and H2 |
Other off-site open space enhancements, recreational improvements, walking / cycling routes and ecological mitigation |
Community and baseline identified priorities supported under various AAP Environment, Open Space and Landscape Strategy proposals. To include:
|
Open space, recreational and ecological improvements link to delivery of housing. Works to coincide with completion of early phases of H1 and H2 Walking and cycling improvements link to delivery of local centre and throughout the scheme |
Social, Community, Economic and Transport Measures
ITEM |
RATIONALE |
PHASING |
Local Employment and Training Agreements |
Strong community priority and identified under the AAP Sustainability Strategy (S2). Support for the development of Work Based Co-ordinators to assist in securing employment and skills development for local people as part of the construction phases of the development and with end site occupiers. Ensure new college provides appropriate re-training to allow people to access new job opportunities. Work with local firms on other skills / workforce development initiatives including environmental management systems. |
Linked to approval of first planning applications for construction works |
Enterprise and Business Support |
Community and socio-economic baseline priorities, identified under the AAP Sustainability Strategy (S2). Support for local business surgeries and coaching as well as social enterprise development. Links to affordable business space, local centre small retail units and RIS. |
Linked to start of works on mixed use and employment quarters |
Safer Communities |
Community priorities and baseline report priorities, identified under the AAP Sustainability Strategy (S2). Contribution towards roll out of local anti-crime and disorder projects (including CCTV), fire prevention programmes, community warden network and neighbourhood policing. |
Timetable linked to early residential developments |
Healthy living and sports development |
Identified through various baselines and consultation, identified under the AAP Sustainability Strategy (S2). Contribution towards innovative and partnership-led health outreach services and facilities to support healthy living initiatives with local residents and employers within both Birmingham and North Worcestershire Primary Care Trust areas. Support for active living and commuting projects as well as sports development programmes connected with Cofton Park. |
Programme Timetable linked to outreach work ahead of new centre opening |
Lifelong Learning |
Socio-economic baseline identified issues and supported under the AAP Sustainability Strategy (S2). To include support for local learning initiatives focused upon basic skills, literacy/numeracy programmes, emergent and advanced readers, early years, family learning, children and young people, older learners and links to further and higher education and new library services. |
Programme timetable linked to opening of new Cofton library at East Works |
Community Cohesion and Inclusion |
Socio-economic and EINA identified priorities and supported under the AAP Sustainability Strategy (S2). To include support for local citizenship programmes and social inclusion projects. Libraries can support social inclusion through facilitating or simply providing space for community activities. |
Throughout development, starting on completion of early phases of development |
Heritage and Culture |
Cultural baseline identified issues and supported under the AAP Sustainability Strategy (S2). To include support for project officers and programmes of directed and informal cultural activities including poetry and live literature events, tours, music programmes, storytelling, reminiscence, exhibitions, local history resources, arts development, sports clubs, carnivals, festivals and holiday programmes. Strong links to ‘The Austin’ building and new Cofton Hackett Library/ Community Centre. |
Links with development of new library at East Works and ‘The Austin’ building. |
Sustainable transport and off-site mitigation |
Identified in the Travel Management Strategy and Movement Strategy (T11/T15). Funding for travel plan co-ordinator. Required to achieve the target modal share. Also green travel plans, car clubs, car-share and individualised travel plan initiatives. Residents’ parking schemes also required to assist in minimising street parking in adjoining residential areas. |
Linked to requirements of Site Wide Travel Plan and more detailed travel plans for specific users |
S106 and Longbridge Infrastructure Tariff Administration |
Administrative costs associated with managing and monitoring S106 agreement and LIT. Standardised % formula adopted |
January 2009 onwards linked to first approved planning permissions |
4.14 Some of the Community Infrastructure improvements may need to be delivered upfront and at certain phased intervals in the overall development schedule. This means that the planning contributions model will require a degree of forward funding to support regeneration and development. The role of the Accountable Body and its banking role will therefore be essential in this respect. The banker and other stakeholders will be expected to demonstrate that all reasonable endeavours have been undertaken to minimize unnecessary expenditure and to identify funding where there is a gap between scheme expenditure and income. (4)
4.15 The rate established for the LIT is detailed in 4.15 and Table 3, which covers both residential and non-residential elements of the scheme. A de minimus level of 5 dwellings has been set for the residential component of the tariff and a minimum of 0.1ha gross for nonresidential sites.
4.16 All financial contributions will be ‘index linked’ from April 2008, in accordance with the methodology set out in the AAP Glossary. The timing and phasing of tariff payments is established below: Residential and Non-Residential
Table 3: Longbridge Infrastructure Tariff (LIT)
RESIDENTIAL |
£ PER DWELLING |
Per Dwelling - Including Affordable Housing |
£16,500 |
NON RESIDENTIAL |
£ SQM |
A1 Superstore |
280 |
A1 Shops (other) – A5 |
120 |
B1 (a) Office |
120 |
B1 (b)/(c) Research and Development/Light Industry |
30 |
B2 Industrial |
30 |
B8 Storage & Distribution |
30 |
C1 Hotels |
50 |
C2 Residential Institutions |
50 |
D1 College |
30 |
D2 Leisure |
50 |
Other |
30 |
4.17 The planning and phasing of the Longbridge development needs to be carefully managed and structured to minimise disruption to local businesses and residents. It also needs to follow the guiding principle that services, facilities and infrastructure will be provided at stages in the development process when the need for them is programmed to arise and not towards the middle or end of a scheme.
4.18 There is a diverse range of infrastructure improvements to deliver the requirements of the LAAP, ranging from key strategic transport infrastructure to those that deliver community and social benefits. The expenditure of infrastructure monies will need to be spent against a detailed delivery plan, which sets out:
The delivery plan will also be reviewed regularly in light of planning application submissions, viability assessments and changing infrastructure costs, tariff income and expenditure profiles.
4.19 The key estimated development phases are detailed below:
Site Remediation
Highways Works, Transport Infrastructure and River Networks
Development Construction and Key Physical Community Infrastructure
Delivery will however be dependant on market conditions at the time of the Development.
4.20 An outline housing trajectory for the overall development is detailed below in Table 4.
Table 4 Longbridge Housing Trajectory
|
2009/10 |
2010/11 |
2011/12 |
2012/13 |
2013/14 |
2014/15 |
2015/16 |
2016/17 |
Total |
Projected Completions Total |
0 |
100 |
240 |
240 |
240 |
240 |
240 |
150 |
1450 |
Market Housing |
0 |
65 |
156 |
156 |
156 |
156 |
156 |
97 |
942 |
Affordable Housing |
0 |
35 |
84 |
84 |
84 |
84 |
84 |
53 |
508 |
4.21 Following the restructuring of MG Rover in 2000, nearly 30 ha of the site was identified as being surplus to requirements and was acquired by St. Modwen PLC and Advantage West Midlands (AWM). The Longbridge Development Framework was prepared for this site by Birmingham City Council and outline planning permission for a major development on the former North Works Car Park and part of South Works was granted in 2005 comprising:
4.22 Following the closure of MG Rover in 2005, a statement of intent was adopted by Birmingham City Council, Bromsgrove District Council and Worcestershire Country Council with endorsement by AWM and the major landowner St. Modwen PLC. This statement had as its aim to:
4.23 The range of development now proposed in this AAP requires a number of phased planning applications. Broadly, the forward planning application process includes:
4.24 The transport and environmental assessments will need to cover the cumulative impact of all development in the AAP area, including North Works, West Works, East Works, Cofton Centre and the existing technology park.
4.25 It is recognized that market conditions are subject to change, and that these can impact on the viability of development. If at the time planning applications are submitted, it can be shown through an open development appraisal, that a scheme may be unviable if the LAAP’s policies have to be applied in full; then the Local Authorities will enter into detailed negotiations with the applicants to determine what may be acceptable to enable the scheme to proceed.
In such cases, the planning obligations that have not delivered the full tariff levels set out in table 3 will include mechanisms to allow the scale of obligations to be increased if it can be demonstrated that market conditions improve at the time the development is implemented. e.g. through linking the tariff payments to phases of the development.
4.26 The plan has been developed in partnership with a wide range of local people, organisations and stakeholders over the last 2-3 years.
4.27 It is now apparent that as the plan moves forward from production to implementation there is a need to clearly set out the key delivery partnerships.
These are briefly outlined below with principal responsibilities:
4.28 There are three main Local Strategic Partnerships which cover the AAP area. In addition to reporting on specific themes or projects to various meetings, and the existing relationships through the various groups detailed above, it is intended that the Longbridge Implementation Group will provide an annual update to each partnership linked in with the annual monitoring requirements of the plan.
4.29 Additionally, although not a formal partnership, the developer is also preparing a scheme of delivery and management for the RIS in consultation with AWM, CTB, BCC and other relevant stakeholders including local Universities.
4.30 A summary implementation plan linking proposals to delivery is outlined below. The table also makes reference to risk assessment and scheme phasing as detailed above.
Table 5: Summary Implementation Plan
AAP Proposals and Policy |
Responsible Bodies |
Delivery Mechanisms |
Delivery Funding |
Land use and Planning Issues |
Phasing and Timetable |
Risk Assessment |
Proposal S1- Sustainability Building Standards |
Applicants/ Planning Authority |
Planning applications and building regulations |
Private sector and Homes and Communities Agency (HCA) |
Requires creative and integrated approach to delivering sustainable buildings |
Progressive standards set from 2008, with increasingly challenging standards required during the lifespan of the development |
Limitations of current technology and increased cost implications of piloting techniques/ approaches |
Proposal S2- Site Wide Sustainability Criteria |
Applicants/ Planning Authority |
Planning Applications and site masterplans |
Private sector and Lottery Funding RFA |
Requires integrated and comprehensive approach to new developments |
From 2008 with first planning application |
Lack of co-ordination |
Proposal DS1- Design Principles |
Applicants/ Planning Authority |
Site masterplans, planning applications and S278 agreements |
Private sector |
Requires the production of high quality site masterplans and supporting design information including codes where necessary |
From 2008 |
Lack of quality in design and architecture. |
Proposal LC1 and LC2 Learning Quarter |
Landowner/ Bournville College |
Planning applications |
-LSC, Bournville College, AWM, -S106 agreement |
Requires integrated approach with other developments in local centre, River Rea enhancements, urban park and provision of access |
Start on site 2009 following completion of remediation works. Completion 2011 |
Lack of coordination and focus. Insufficient resources |
Proposal LC1 and LC3 Retail Quarter |
Landowner/ Private Sector |
-Planning applications - Private organisations programmes S106 agreements |
Private sector |
Requires integrated approach with other developments in local centre, River Rea enhancements, urban park and provision of access |
Start on site 2009 following completion of remediation works. Completion 2012 onwards |
Downturn in the economy combined with continued competition from on-line retailers |
Proposal LC1 and LC 4- Mixed use quarter including housing, heritage building, offices |
Landowner/ Private sector |
-Planning applications - Private organisations programmes - S106 agreements |
- Private sector - RSL - Lottery Funding |
Requires integrated approach with other developments in local centre, River Rea enhancements, urban park and provision of access |
Start on site 2011 |
Development risk spread across range of land uses. |
Proposal EZ1 |
Landowner/ Private sector |
- Planning applications - S106 agreements - Business support programmes |
- Private sector - RFA - HCA |
Requires integrated approach with developments in local centre, and provision of access |
Start on site 2011 |
- Downturn in economy - Low take-up of space |
Proposal RIS 1 |
Landowner/ Private sector with RIS management and delivery body |
-Planning applications - S106 agreements - Business support programmes |
- Private sector - RFA - HCA |
Requires integrated approach with River Rea enhancements, flood compensation measures, and provision of access |
First phase start on site 2011 |
- Downturn in economy - RIS competition from other locations - Low take-up of technology space - Ineffective marketing |
Proposal H1 – Housing on West works |
Private sector/ RSL |
-Planning applications - S106 agreements |
- Private sector - RSL |
Requires integrated approach with, River Rea enhancements, flood compensation measures, provision of neighbourhood car park and provision of access |
Start on site 2011 |
Stagnation in market for private sector housing or too much housing coming onto market in area at same time |
Proposal H2- East works housing |
Private sector/ RSL |
Planning applications including site masterplan S106 agreements |
- Private sector - RSL |
Requires coordinated integrated approach and attention to River Arrow corridor and community facilities. |
Start on site 2010 |
Stagnation in market for private sector housing or too much housing coming onto market in area at same time |
Proposal EZ2 Nanjing |
NAC / Landowner |
Planning applications |
Private sector |
Need to balance employment uses with compatible land uses across the site |
Handback of surplus land from 2007 |
Large proportion of the site dominated by single employer. Stiff competition and potential downturns in automotive industry |
Proposal EZ 3- Cofton Centre |
Private sector/ landowner |
Planning applications |
Private sector |
Need to provide quality well-connected built environments associated with more traditional employment uses |
Planning applications approved in 2007. Work ongoing |
Economic downturn |
Transport and Movement Strategy (T1-15) |
Public/Private Sectors |
Planning applications S106 and S278 agreements |
- Private Sector - Local Authorities - Stakeholders - Funding Programmes |
Needs highly co-ordinated approach with appropriate infrastructure provided at the right time to serve the development |
Start on site 2009 |
Poor patronage of public transport. Lack of resources |
Environment Open Space and Landscape Strategy (OS1-17) |
Landowners/ Public Sector/ Private Sector |
Planning applications/ S106 agreements |
- Private Sector - Local Authorities - Stakeholders - Funding Programmes |
Needs comprehensive masterplan for Cofton Park and appropriate implementation and management plans |
Start 2009 following completion of remediation works |
Lack of sufficient resources and maintenance |
4.31 The implementation of the Area Action Plan will be monitored on an annual basis against the plan’s objectives detailed in Part B. This will help BCC and BDC keep track of progress during the lifespan of the plan. A number of Key Performance Indicators (KPIs) have been identified, which will be refined over time and linked to appropriate targets. These targets will then be reported though the Annual Monitoring Report. The responsibility for the collection of the KPI information resides with both planning authorities. This will involve the collection of primary and secondary data from a variety of sources.
4.32 In addition to annual monitoring requirements the plan will be subject to a strategic review after 5 years. This will assist the planning authorities gauge the overall effectiveness of the plan and consider any major changes in direction, policies and proposals. Table 6 sets out a series of indicators against which progress will be monitored.
Table 6: Longbridge AAP Monitoring Requirements
Sustainable Development
AAP Themes and Objectives |
AAP Proposals and Policy |
Key Performance Indicators (KPI) |
Indicator Cross References |
Information Collection |
Responsibility |
Obj. 1- Sustainable Communities |
S2, LC1, H1 and H2 |
KPI1: Percentage of people surveyed who feel that their local area is a place where people from different backgrounds get on well together |
Home Office Quality of Life Indicator
|
Requires Community Survey
|
BCC/BDC |
|
|
KPI2: Extent of individuals’ a) participation and b) active involvement in voluntary and community activities |
Home Office Citizenship Survey |
Requires Community Survey |
BCC/BDC |
|
|
KPI3: Percentage of residents who feel ‘fairly safe’ or ‘very safe’ after dark while outside in the local area |
SA Monitoring Framework/ONS BDC LDF Indicator/ Objective S05 |
Links to Community Survey |
BCC/BDC |
|
|
KPI4: Socio-economic mix of the population |
Census 2011/ WMRSS Headline Indicator |
Collation of Census data |
BCC/BDC |
|
|
KPI5: Numbers of social and community enterprises |
SA Monitoring Framework/ |
Annual Business Survey |
BCC/BDC |
Obj. 2- Sustainable Buildings and Infrastructure |
S2 |
KPI 9: Reduction in carbon dioxide (CO2) emissions produced in the AAP area |
BCC Sustainable Community Strategy |
Utilisation of assessment tool |
BCC/BDC |
|
|
KPI10: Climate change adaptation measures in the AAP area |
BCC Sustainable Community Strategy |
Collection of information on projects |
BCC/BDC |
|
|
KPI 11: Increase in the percentage of household waste sent for recycling |
Links to Draft BCC Municipal Waste Management Strategy (BVPI 82a) |
Waste collection data |
BCC/BDC |
|
|
KPI 12: Reduction in the weight (in kilograms) of household waste collected per head of the population |
Links to Draft BCC Municipal Waste Management Strategy (BVPI 84) |
Waste collection data |
BCC/BDC |
Obj. 2- Sustainable Buildings |
S1 |
KPI6: Renewable energy capacity installed by type |
BCC LDF Core Output Indicator 9 |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
|
|
KPI7: Number of new residential units meeting CSH levels 4, 5 and 6 (separate) for a) energy efficiency standards and b) water conservation standards |
WMRSS Output / Outcome Indicator |
Planning applications and building regulation information |
BCC/BDC |
|
|
KPI8: Number of commercial developments compliant with BREEAM Very Good and Excellent Standards (separate) |
AAP Local Indicator BDC LDF Indicator/ Objective EV10 |
Planning applications and building regulation information |
BCC/BDC |
Obj.3- Quality Connected Open Spaces |
OS1-17 |
KPI9: Number of eligible open spaces managed to “green flag award” standard |
Links to BCC LDF Core Output Indicator 4c. Links to Indicator/ Objective S07, EV2 |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
|
|
KPI38: Achievement of Accessible Natural Greenspace Standards |
SA Monitoring Framework / EN |
Links to SA Monitoring Requirements |
BCC/BDC |
|
|
KPI10: Provision of open space: (i) Net loss/gain in amount of public open space and public and private playing fields; (ii) Percentage of new dwelling completions within reasonable walking distance of public open space |
BCC LDF Local Indicator 4d. BDC LDF Indicator/ Objective S07 |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
|
|
KPI11: Change in areas and populations of biodiversity importance, including: change in priority habitats and species (by type) |
BCC LDF Core Output Indicator 8(i) |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
|
|
KPI12: Change in areas and populations of biodiversity importance, including: change in areas designated for their intrinsic environmental value including sites of international, national, regional or subregional significance |
BCC LDF Core Output Indicator 8(ii) BDC LDF Indicator/ Objective EV1 |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
Obj. 4- Sustainable Movement |
T1-15 |
KPI13: Percentage of completed non-residential development complying with car parking standards set out in the local development framework |
BCC LDF Core Output Indicator 3a |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
|
|
KPI14: Annual average traffic flow on local road network |
SA Monitoring Framework/AAP Local Indicator Links with BDC LDF Indicator/Objective S08 |
Requires travel pattern survey and traffic modelling |
BCC/BDC |
|
|
KPI15: % of trips across all transport modes to / from AAP area: a) walking, b) cycling, c) bus; d) train; e) car |
AAP Local Indicator |
Requires travel pattern surveys |
BCC/BDC |
Obj. 5- Place Management |
S2, LC1 |
KPI16: % of users satisfied/ very satisfied with local centre facilities |
AAP Local Indicator Links with BDC LDF Indicator/Objective S07 |
Visitor Satisfaction Survey |
BCC/BDC |
|
KPI17: % of users satisfied/ very satisfied with public spaces |
AAP Local Indicator |
Visitor Satisfaction Survey |
BCC/BDC |
High Quality Places
AAP Themes and Objectives |
AAP Proposals and Policy |
Key Performance Indicators (KPI) |
Indicator Cross References |
Information Collection |
Responsibility |
Obj. 6- Excellence in Design |
DS1 |
KPI18: % of users satisfied/ very satisfied with built form |
AAP Local Indicator Links with BDC LDF Indicator/Objective S06 |
Visitor Satisfaction Survey supported by CABE review |
BCC/BDC |
Economic Transformation
AAP Themes and Objectives |
AAP Proposals and Policy |
Key Performance Indicators (KPI) |
Indicator Cross References |
Information Collection |
Responsibility |
Obj. 7- Regional Investment |
LC1-4, EZ1-3 and RIS1 |
KPI19: Numbers of jobs created or safeguarded |
RDA Core Output Links with BDC LDF Indicator/Objective EC1
|
Planning application information submission Annual occupier telephone survey
|
BCC/BDC |
|
|
KPI20: Inward Investment as percentage of GVA |
SA Monitoring Framework/RDA Output |
Annual occupier survey |
BCC/BDC |
Obj. 8- Protection of employment land |
EZ1-3 and RIS1 |
KPI21: Loss of employment land in development/ regeneration areas |
BCC LDF Core Output Indicator 1e. BDC LDF Indicator/ Objective EC2 |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
Obj. 9-RIS |
RIS1 |
KPI22: Amount of land developed for employment by use type. |
BCC LDFCore Output Indicator 1b |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
|
|
KPI23: RIS a) Number of businesses attracted to RIS and b) Quantity of Floorspace Let |
AAP Local Indicator |
RIS occupier survey | BCC/BDC |
|
|
KPI24: Number of businesses within RIS assisted to engage in new collaborations with the UK knowledge base |
Links to RDA Regional Core Output |
RIS occupier survey | BCC/BDC |
|
|
KPI25: Growth rates and linkages in A38 High Technology Corridor |
SA Monitoring Framework/ RDA output |
RIS occupier survey |
BCC/BDC |
|
|
KPI26: Research and development and employment in high technology and medium technology industries |
SA Monitoring Framework/DTI |
RIS occupier survey |
BCC/BDC |
Obj. 10- Accessible employment and training |
S2, LC2 |
KPI27: Number of people assisted to get a job by a) ward and b) types of jobs |
Links to RDA Core Output and WMRSS Headline Indicator Links with BDC LDF Indicator/Objective EC3 |
Annual review through Longbridge Skills and Employment Group |
BCC/BDC |
Obj. 11- Supporting local enterprise |
S2, LC1, LC3, LC4, EZ1-3 and RIS1 |
KPI28: Number of new businesses created and demonstrating growth after 12 months |
RDA Core Output |
Annual Business Survey |
BCC/BDC |
|
|
KPI29: Number of businesses attracted to the AAP area |
Links to RDA Core Output |
Annual Business Survey |
BCC/BDC |
|
|
KPI30: Number of business supported using business start-up units |
Local AAP Indicator |
Annual Business Survey |
BCC/BDC |
|
|
KPI31: Number of new VAT registrations in Longbridge as a percentage of total (annual) |
SA Monitoring Framework/ RDA Output |
Annual Business Survey |
BCC/BDC |
A New Heart for Longbridge
AAP Themes and Objectives |
AAP Proposals and Policy |
Key Performance Indicators (KPI) |
Indicator Cross References |
Information Collection |
Responsibility |
Obj. 12- Mixed Use Local Centre |
LC1-LC4 |
KPI32: Amount of floorspace completed by retail, office and leisure development |
Links to BCC LDF Core Output Indicator 4a |
Needs to be compliant with LDF reporting requirements (BCC/BDC) (floorspace limits details in AAP) |
BCC |
Homes for the Future
AAP Themes and Objectives |
AAP Proposals and Policy |
Key Performance Indicators (KPI) |
Indicator Cross References |
Information Collection |
Responsibility |
Obj. 13- Delivering new homes |
|
KPI33: Longbridge housing trajectory i ) net additional dwellings since the start of the AAP (ii) net additional dwellings for the current year; (iii) projected net additional dwellings up to the end of the AAP (iv) the annual net additional dwelling and (v) annual average number of net additional dwellings needed to meet overall housing requirements, having regard to previous years’ performances |
BCC LDF Core Output Indicator 2a BDC LDF Indicator/ Objective S01
|
Needs to be compliant with LDF reporting requirements (BCC/BDC)
|
BCC/BDC |
|
|
KPI34: Percentage of new dwellings completed at: (i) less than 30 dwellings per hectare; (ii) between 30 and 50 dwellings per hectare; (iii) above 50 dwellings per hectare. |
BCC LDF Core Output Indicator 2c. |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
|
|
KPI35: Provision of recycling facilities integral/close to homes |
SA Monitoring Framework/ Local AAP Indicator BDC LDF Indicator/ Objective EV5 |
Needs to link to waste recycling plans/strategies and reporting requirements |
BCC/BDC |
Obj. 14- Mixed and affordable housing |
LC1, H1 and H2 |
KPI36: Number of affordable housing completions |
BCC LDFCore Output Indicator 2d. BDC LDF Indicator/ Objective S01 |
Needs to be compliant with LDF reporting requirements (BCC/BDC) |
BCC/BDC |
Overall Objectives |
All key proposals |
KPI37: Carbon Footprint of the development |
SA Monitoring Framework/ Local AAP Indicator |
Needs to link to approaches/ methodology adopted on other schemes |
BCC/BDC |
4. The banking function will be administered in accordance with local authority accounting regulations and principles. The banker may provide deficit funding to the LIT Fund to enable essential development works to take place in advance of receipts, subject to certain financial limits. All costs incurred under the banking function will be charged against the LIT Fund.